勘察 地基 土木 土建 实习报告(CFG桩)

河南城建学院

《勘查技术与工程》

实习报告

专    业   勘查技术与工程     

实习类别             

时    间 20##-2012(1)12-15

指导老师                      

学    号                      

姓    名                      


目       录

一、实习目的和任务························································································1

二、实习概述··································································································1

1.实习地点·····························································································1

2.工程概况·····························································································1

3.实习工作·····························································································2

三、实习内容··································································································2

1.CFG桩复合地基设计对勘察的要求·······················································2

2.CFG桩复合地基承载力计算··································································2

3.CFG桩复合地基设计·············································································3

1)设计思想······················································································3

2)复合地基设计及设计参数确定······················································4

3)布桩·····························································································5

4.长螺旋钻管内泵压CFG桩施工工艺·······················································6

1)施工设备······················································································6

2)CFG桩施工····················································································6

3)CFG柱施工中常见的问题及质量控制············································7

(1)堵管···················································································7

(2)窜孔···················································································7

(3)钻头阀门打不开·································································8

(4)桩体上部存气·····································································8

(5)先提钻后泵料·····································································8

5.施工检验及验收···················································································9

1)施工检测····················································································9

(1)CFG桩的检测·····································································9

(2)CFG桩复合地基的检测·······················································9

2)CFG桩复合地基施工验收····························································9

四、实习心得·································································································10

五、附录········································································································11

1.拟建建筑首层平面图··········································································12

2.CFG钻杆钻头图··················································································13


一、实习目的和任务

生产实习是勘查技术与工程专业教学计划的重要组成部分,是学生在校期间理论联系实际,增长实践知识的主要手段和方法之一。通过实习,使学生在学校所学到的理论知识与生产实践相结合,综合运用所学到的知识解决生产实践中遇到的问题,并验证、巩固和深化所学的理论知识,培养学生分析问题和解决问题的能力,通过亲身参与施工组织管理工作和参加一定的专业劳动,对系统了解专业情况,加深对专业理论知识的全面理解起着重要作用,同时也对顺利实现有学校到社会的转化,为毕业生能尽快胜任工作,打下一个良好的基础。

实习的具体任务是:

1.通过实习,巩固已学过的理论知识,尤其是专业理论知识;

2.在教室实习和理论学习的基础上,进一步增强钻探工程、基础工程、工程勘察、掘进工程施工的感性知识,全面熟悉施工过程、掌握钻探工程、基础工程施工、工程勘察、掘进工程施工的基本知识和基本技能。

3.为今后从事钻探工程、基础工程、工程勘察、掘进工程、岩土工程等领域的工作,分析解决实际工作只中的技术问题、实验研究新工艺、新方法打下实践基础。

二、实习概述

1.实习地点

河南省商丘市夏邑县南桥西北角,公园·蓝波湾四期工程

2.工程概况

夏邑公园·蓝波湾工程位于夏邑县新区南桥西北角,紧邻古运河城,环境优美。小区风格是西班牙建筑风格。96m2至139m2是其主力户型。占地面积71928m2,建筑面积110000 m2,总投资15000万,绿化率40%,总户数为800。

公园·蓝波湾四期工程拟建建筑物由门面房和商品房组成。设计地上10层,地下1层;为框架——剪力墙结构;地下车库为地下1层,剪力墙结构。基础底板筏板基础。±0.00=25.5m。楼基础底板标高-7.3m,槽底标高-7.48=18.02m,地下车库基础槽底标高-6.98= 18.52m。楼座核心区基底平均压力标准值为560KPa,其余(边缘区)范围基底平均压力标准值为230KPa。

根据商丘市勘察设计研究院有限公司提供的《夏邑公园·蓝波湾项目岩土工程勘察报告》, 主楼楼座基底座落在新近沉积的第2大层(②层)。地基承载力标准值(fka)为170kPa不能满承载力要求,故需要进行地基处理。

采用CFG桩复合地基,以满足承载力并保证差异沉降控制在允许范围。CFG桩复合地基的要求如下:主体结构产生的地基净反力标准值详平面,地基处理后的长期最大沉降量Smax≤50mm,倾斜变形许值可为0.0015。车库及其他建筑单元采用天然地基。

3.实习工作

跟随CFG桩机做打桩准备和打桩工作。

三、实习内容

1.CFG桩复合地基设计对勘察的要求

按照国家标准《岩土工程勘察规范》GB50021--2001进行岩土工程勘察,并提供勘察报告。

(1)工程勘察内容

①查明岩土埋藏条件及物理力学性质、持力层及下卧软弱土层埋藏深度、厚度、性质及变化。

②查明水文地质条件、地下水位、地下水对混凝土的腐蚀性。

③查明填土厚度、填土时间以及填土材料的组成成分。若基础底面在填土层,应给出填土层的承载力特征值。

(2)勘探点间距

勘探点的布置应控制持力层层面坡度、厚度及岩土性状,其间距为10~30m。层面高差或岩性变化较大时,间距取小值。

(3)勘探深度

应取勘探总数的1/3~1/2作为控制孔,深度为桩尖以下基础宽度的1~5倍。

(4)室内试验

完成土的物理力学性质常规实验。

对基础底面以下的土层进行灵敏度试验。查明这些土层灵敏度的大小,为褥垫层施工提供依据。对中、高灵敏度土,褥垫层施工时尽量避免对桩间土的扰动,防止产生“橡皮土”。

(5)勘察报告

除按国家标准提供勘察报告外,尚需特别提供或增加以下内容:

①提供各土层的桩侧阻力和桩端阻力,桩侧阻力和桩端阻力一般按相同施工工艺的混凝土桩提供。

②若有填土,应说明填土材料的构成及填土时间,尤其需要对可能给施工造成困难的工业垃圾或块石等予以说明;当基础底面在填土层上时,需提供填土承载力特征值。

③提供基底以下土层的灵敏度,作为褥垫层铺设施工时选择施工设备和施工工艺的依据。

④提供场地土层压缩试验曲线,并以表格形式给出不同压力p所对应的孔隙比e,作为变形计算的依据。

⑤对基底以下各主要土层必须提供其承载力特征值,作为复合地基的设计依据。

2.CFG桩复合地基承载力计算

复合地基是由桩间土和增强体(桩)共同承担荷载的。目前复合地基承载力的计算公式比较多,但应用比较普遍的有两种,其一是将桩间土承载力和单桩承载力进行合理组合叠加;其二是将复合地基承载力用天然地基承载力扩大一个倍数来表示。

必须指出,复合地基承载力不是天然地基承载力和单桩承载力的简单叠加,需要对如下的一些因素予以考虑:

(1)施工时对桩间土是否产生扰动或挤密,桩间土承载力有无降低或提高。

桩间土当竖直方向上荷载不大时,对土起阻碍变形的作用,使土的沉降减少;荷载较大时,起增大变形的作用。

(3)复合地基中桩的Q-s线呈加工硬化型,比自由单桩的承载力要高。

(4)桩和桩间土承载力的发挥都与变形有关,变形小时,桩和桩间土承载力的发挥都不充分。

(5)复合地基桩间土承载力的发挥与褥垫层厚度有关。

3.CFG桩复合地基设计

1)设计思想

当CFG桩桩体强度用得较高时,具有刚性桩的性状,有的设计人员常将其与桩基础相联系,因此讨论一下CFG,桩复合地基与桩基础的区别显然是十分必要的。

桩基础是一种常用的基础类型,桩在桩基础中既可承受竖向荷载,也可承受水平荷载。众所周知,桩是一种细长杆件,它传递水平荷载的能力远远小于传递竖向荷载的能力,设计时采用桩基础承受竖向荷载是扬其长,承受水平荷载是用其短。

CFG桩复台地基通过褥垫层把桩和承台(基础)断开,改变了过分依赖于桩承担竖向荷载和水平荷载的传统设计思想。

当基础承受水平荷载Q时,有三部分力与Q相平衡:其一为基础底面摩擦力Ft;其二为基础两侧面的摩擦力F1;其三为与水平荷载Q方向相反的土的抗力R。

Ft和基底与褥垫层之间的摩擦系数μ及建筑物重量W有关,W数值越大,Ft越大。

基底摩擦Ft,传递到桩和桩间土上,桩顶剪应力为τp,桩间土剪应力τs。由于CFG桩复合地基面积置换率一般不大于10%,故有不低于90%的基底面积的桩间土承担了绝大部分水平荷载,而桩承担的水平荷载仅占很小一部分。前已述及,桩土剪应力比随褥垫层厚度的增大而碱小。设计时可通过改变褥垫层厚度调整桩土水平荷载分担比。

竖向荷载的传递,如何在桩基中发挥桩间土的承载能力是许多学者都在探索的课题。大桩距布桩的“疏桩理论”就是为调动桩间土承载能力而形成的新的设计思想。

在桩基中,桩只存在向下刺入的可能。当承台承受垂直荷载时,对于摩擦桩,桩端向下刺入.承台发生沉降变形,桩间土可以发挥一定的承载作用,且沉降变形越大,桩间土的作用越明显;桩距越大,桩间土发挥的作用也越大。对于端承桩,承台沉降变形一般很小,桩间土承载能力很难发挥。需要指出的是,即使是摩擦桩,桩间土承载能力的发挥占总承载能力的百分比也很小,且较难定量预估。

CFG桩复合地基通过褥垫层与基础连接,无论桩端落在一般土层还是坚硬土层,均可保证桩间土始终参与工作。因此竖向承载力设计首先是将士的承载力充分发挥,不足的部分由CFG桩来承担。由于CFG桩复合地基置换率不高,基础下桩间土承受的荷载是一个不小的数值。总的荷载扣除桩间土承担的荷载.才是CFG桩应承受的荷载。显然,与传统的桩基设计思想相比.桩的数量可以大大减少,再加上CFG桩不配筋,桩体利用工业废料粉煤灰作为掺加料,大大降低了工程造价且保护了环境。

需要特别指出的是,CFC桩不只是用来加固软弱地基,对于较好的地基土,若建筑物荷载较大,天然地基承载力不足或变形不能满足要求,也可以采用CFG桩进行加固处理。

在设计中,CFG桩不仅可以采用同一桩长,也可以根据设计条件和地质条件采用不同桩长间隔布置(长短桩复合地基),甚至CFG桩与其他桩型组合,如CFG桩与夯实水泥土桩、碎石桩等间隔布置,形成多桩型复合地基。

2)复合地基设计及设计参数确定

复合地基设计除满足地基承载力和变形条件外,还要考虑以下诸多因素进行综合分析来确定设计参数。

(l)施工设备和施工工艺

复合地基设计时需考虑采用何种设备和工艺进行施工,选用的设备穿透土层的能力和最大施工桩长能否满足要求.施工时对桩间土已打桩是否会造成不良影响。

(2)场地土质变化

场地土质的变化对复台地基施工工艺的选择和设计参数的确定有着密切的关系,因此在设计时要认真阅读勘察报告,对基底土有一个全面的认识。通过对场地土的了解,对荷载情况、地基处理要求等综合分析,考虑采用何种布桩形式。

(3)场地周围环境

场地周围环境是设计时确定施工工艺的一个重要因素。当场地离居民区较近时,或场地周围有精密设备仪器的车间和试验室以及对振动比较敏感的管线,施工不宜选择振动成桩工艺,而应选用无振动低噪音的施工工艺,如长螺旋钻管内泵压CFG法;若场地位于空旷地区,且地基土主要为松散的粉细砂或填土,选用振动沉管打桩机是适宜的。

(4)建筑物结构布置及载荷传递

目前CFG桩应用于高层建筑的工程越来越多,地基处理设计时要考虑建筑物结构布置及荷载传递特性。例如,建筑物是单体还是群体,体形是简单还是复杂,结构布置是均匀还是存在偏心,主体建筑物周围是否存在地下车库之类的大开间结构,建筑物是否存在转换层或地下大空间,建筑物通过墙、柱和核心筒传到基础的荷载扩散到基底的范围及均匀性等。在设计时必须认真分析结构传递荷载的特点以及建筑物对变形的适应能力,做到合理布桩,方可保证地基处理达到预期目的。

(5)地基处理目的

设计时必须明确地基处理是为了解决地基承载力问题、变形问题还是液化问题,解决问题的目的不同,采用的工艺、设计方法、布桩形式均不同。

CFG桩复合地基设计主要确定以下5个设计参数,分别为桩长、桩径、桩间距、桩体强度、褥垫层厚度及材料:

①桩长    CFG桩复合地基要求桩端落在好的土层上,这是CFG桩复合地基设计的一个重要原则。因此,桩长是CFG桩复合地基设计时首先要确定的参数,它取决于建筑物对承载力和变形的要求,土质条件和设备能力等因素。设计时根据勘察报告分析各土层,确定桩端持力层和桩长,并计算单桩承载力。

②桩径d    CFG桩桩径的确定取决于所采用的成桩设备,一般设计桩径为300-600mm。

③桩间距s    一般桩间距s=(3~5)d,桩间距的大小取决于设计要求的复合地基承载力和变形、土性与施工机具。一般设计要求的承载力高时s取小值,但必须考虑施工时相邻桩之间的影响,就施工而言,希望采用较大的桩距和较长的桩长,因此s的大小应综合考虑。

④桩体强度    原则上,桩体配比按桩体强度控制,桩体试块抗压强度应满足下式要求。

式中fcu——桩体混合料试块(边长1500mm立方体)标准养护28d立方体抗压强度平均值(kPa);

Ra——单桩竖向承载力特征值(kN);

Ap——桩的截面积(m2)。

⑤褥垫层厚度及材料褥垫层厚度一般取10~30cm为宜,当桩径和桩间距过大时,结合对土性的考虑,裤垫层厚度还可适当加大。褥垫层材料可用粗砂、中砂、碎石、级配砂石(最大粒径不大于30 mm)。

3)布桩

原则上,CFG桩可只在基础范围以内布桩。

对于墙下条形基础,在轴心荷载作用下,可采用单排、双排或多排布桩,且桩位宜沿轴线对称。在偏心载荷作用下,可采用沿轴线非对称布桩。

对于独立基础、箱形基础、筏板基础,基础边缘到桩的中心距一般为1倍桩径或基础边缘到桩边缘的最小距离不宜小于150mm,对条基不宜小于75mm。

对于箱筏基础,底板设计时宜沿建筑物地下室外墙悬挑出来,外墙以外应布桩,如图(a)所示。有些工程,设计的基础外缘与地下室外墙在一个垂直面上,此种情形布桩时·宜在地下室外墙下布置一排桩,如图(b)所示,但不宜采用如图(c)所示的布桩方法。

对于柱(墙)下筏板基础,布桩时除考虑整体荷载传到基底的压应力不大于复合地基的承载力外,还必须考虑每根柱(每道墙和核心筒)传到基础的荷载扩散到基底的范围,在扩散范围内的压应力也必须等于或小于复合地基的承载力。扩散范围取决于底扳厚度,在扩散范围内底板必须满足抗冲切要求。

对可液化地基或有必要时,可在基础外一定范围内设置护桩(可液化地基一般用碎石桩作护桩)。布桩时要考虑桩受力的合理性,尽量利用桩间土应力σs产生的附加应力对桩侧阻力的增大作用。通常σs越大,作用在桩上的水平力就越大,桩的侧阻力也越大。

4.长螺旋钻管内泵压CFG桩施工工艺

1)施工设备

长螺旋钻管内泵压CFG桩施工工艺是由长螺旋钻机、混凝土泵和强制式混凝土搅拌机组成的完整的施工体系。其中长螺旋钻机是该工艺设备的核心部分。目前长螺旋钻机根据其成孔深度分为12 m、16 m、18m、24 m和30m等机型,施工前应根据设计桩长确定施工所采用的设备。

2)CFG桩施工

(1)钻机就位    CFG桩施工时,钻机就位后,应用钻机塔身的前后和左右的垂直标杆检查塔身导杆,校正位置,使钻杆垂直对准桩位中心,确保CFG桩垂直度容许偏差不大于1%。

(2)混合料搅拌    混合料搅拌要求按配合比进行配料,计量要求准确,上料顺序为:先装碎石或卵石,再加水泥、粉煤灰和外加剂,最后加砂,使水泥、粉煤灰和外加剂夹在砂、石之间,不易飞扬和附着在筒壁上,也易于搅拌均匀。每盘混合料搅拌时间不应小于60s。混合料坍落度控制在16~20cm。在泵送前,混凝土泵料斗、搅拌机搅拌筒应备好熟料。

(3)钻进成孔    钻孔开始时,关闭钻头阀门,向下移动钻杆至钻头触及地面时,启动发动机钻进。一般应先慢后快,这样既能减少钻杆摇晃,又容易检查钻孔的偏差,以便及时纠正。在成孔过程中,如发现钻杆摇晃或难以钻进时,应放慢进尺,否则较易导致桩孔偏斜、移位,甚至使钻杆、钻具损坏。钻进的深度取决于设计桩长,当钻头到达设计桩长预定标高时,应在与动力头底面停留位置相应的钻机塔身处做醒目标记,作为施工时控制桩长的依据,正式施工时,当动力头底面到达标记处,桩长即满足设计要求。施工时还应该考虑施工工作面的标高差异,做相应增减。

在钻进过程中.当遇到圆砾层或卵石层时,会发现进尺明显变慢,机架出现轻微晃动。在有些工程中.可根据这些特征来判定钻杆进入圆砾层或卵石层的深度。

(4)灌注及拔管    CFG桩成孔到设计标高后,停止钻进,开始泵送混台料,当钻杆芯管充满混合料后开始拨管,严禁先提管后泵料。成桩的提拔速度宜控制在2~3m/min,成桩过程宜连续进行,应避免因后台供料缓慢而导致停机待料。若施工中因其他原因不能连续灌注,必须根据勘察报告和已掌握的施工场地的地质情况避开饱和砂土和粉土层,不得在这些土层内停机。灌注成桩后,用水泥袋盖好桩头,进行保护。施工中每根桩的投料量不得少于设计灌注量。

(5)移机    当上一根桩施工完毕后,钻机移位,进行下一根桩的施工。施工时由于CFG桩排出的土较多,经常将邻近的桩位覆盖,有时还会因钻机支撑脚压在桩位旁使原标定的桩位发生移动。因此,下一根桩施工时,还应根据轴线或周围桩的位置对需施工的桩的位置进行复核,保证桩位准确。

3)CFG柱施工中常见的问题及质量控制

(1)堵管    堵管是长螺旋钻管内采压CFC桩施工工艺常遇到的主要问题之一。它直接影响CFG桩的施工效率,增加工人劳动强度,还会造成材料浪费。特别是故障排除不畅时,使已搅拌的CFG桩混合料失水或结硬,增加了再次堵管的几率,给施工带来很多困难

主要有如下几种堵管原因。

①混合料配合比不合理    主要是混合料中的细骨料和粉煤灰用量较少,混合料的和易性不好,从而发生堵管。

②混合料搅拌质量有缺陷    坍落度太大的混合料,易产生泌水、离析。在管道内,水浮到上面,骨料下沉。在泵压作用下,水先流动,骨料与砂浆分离,摩擦力剧增,从而导致堵管。坍落度太小,混合料在管道内流动性差,也容易堵管。施工时合适的坍落度宜控制在16~20cm,若混合料可泵性差,可适量掺入泵送剂。

③设备缺陷    弯头是连接钻杆与高强柔性管的重要部件。若弯头的曲率半径不合理,会发生堵管;弯头与钻杆垂直连接,也会发生堵管;此外,管接头不牢固,垫圈破损也会导致水泥砂浆的流失,造成堵管。有些生产厂家的钻机、钻头设计不合理,密封也不严,在具有承压水的粉细砂中成桩时,承压水带着砂通过钻头孔隙进入钻杆芯管,有时会形成长达50cm的砂塞;当泵入混合料后,砂塞堵住钻头阀门,混合料无法落下,造成堵管。

④冬季施工措施不当    冬季施工时,混合料输送管及弯头处均需作防冻保护,一旦保温效果不好,常在输送管和弯头处造成混台料缩冻,造成堵管。

⑤施工操作不当    钻杆进人土层预定标高后,开始泵送混合料,管内空气从排气阀排出,待钻杆芯管及输送管充满混合料后,应及时提钻,保证混合料在一定压力下灌注成桩。若注满混台料后不及时提钻,混凝土泵一直泵送,在泵送压力下会使钻头处的水泥浆液挤出,同样可使钻头阀门处产生无水泥浆的干硬混合料塞体,使管道堵塞。

(2)窜孔    在饱和粉土和粉细砂层中常遇到这种情况,施工完l号桩后,接着施工相邻的2号桩时,随着钻杆的钻进,发现已施工完且尚未结硬的l号桩桩顶突然下落,有时甚至达2m以上;当2号桩泵入混合料时,能使l号桩下降的桩顶开始回升,泵人2号桩的混合料足够多时,l号桩桩顶恢复到原标高。工程中称这种现象叫窜孔。

实践表明,窜孔发生的条件如下:

①被加固土层中有松散饱和粉土或粉细砂;

②钻杆钻进过程中,叶片剪切作用对土体产生扰动;

③土体受剪切扰动积累的能量,足以使土体发生液化。

大量工程实践证实,当被加固土层中有松散粉土或粉细砂,但投有地下水时,施工未发现有窜孔现象;被加固土层中有松散粉土或粉细砂且有地下水,但桩距很大且每根桩成桩时间很短时.也很少发生窜孔现象;只是在桩距较小,桩的长度较大,成桩时间较长,且成桩时一次移机施打周围桩数量过多时才发生窜孔。

工程中常用的防止窜孔的方法有如下几种。

①对有窜孔可能的被加固地基尽量采用大桩距的设计方案。增大桩距的目的在于减少新打桩对已打桩的剪切扰动,避免不良影响。

②改进钻头,提高钻进速度。

③减少在窜孔区域打桩推进排数,如将一次打4排改为2排或l排。尽快离开已打桩,减少对已打桩扰动能量的积累。

④必要时采用隔桩、隔排跳打方案,但跳打要求及时清除成桩时排出的弃土.否则会影响施工进度。

发生窜孔后一般采用如下方法处理:当提钻灌注混台料到发生窜孔土层时,停止提钻,连续泵送混合料直到窜孔桩混合料液面上升至原位为止。

对采用上述方法处理的窜孔桩,需通过低应变检测或静载荷试验进一步确定其桩身完整性和承载力是否受到影响。

(3)钻头阀门打不开    施工过程中,发现有时钻孔到预定标高后,泵送混合料提钻时钻头阀门打不开,无法灌注成桩。

阀门打不开一般有如下两个原因。

①钻头构造缺陷,如当钻头阀门盖板采用内嵌式时,有可能有砂粒、小卵石等卡住,导致阀门无法开启。

②当桩端落在透水性好、水头高的砂土或卵石层中时,阀门外侧除了土侧向压力外,主要是水的侧压力(水侧压力系数为1)很大。阀门内侧的混合料侧压力小于阀门外的侧压力,致使阀门打不开。当钻杆提升到某高度后,侧压力逐渐减小,管内混合料侧压力不变,当管内侧压力大于管外侧压力时,阔门打开,混合料突然下落。这种情况在施工中经常发生,阀门打不开多为此种情况。

对这一问题,可采用改进阀门的结构形式或调整桩长使桩端穿过砂土而进入黏性土层的措施来解决。

(4)桩体上部存气    截桩头时,发现个别桩桩顶部存有空间不大的空心。这主要是施工过程中,排气阀不能正常工作所致。钻杆成孔钻进时,管内充满空气,钻孔到预定标高开始泵送混合料,此时要求排气阀工作正常,能将管内空气排出。若排气阀被混合料浆液堵塞不能正常工作,钻杆管内空气无法排出,就会导致桩体存气并形成空洞。

为杜绝桩体存气,必须保证排气阀正常工作。施工时要经常检查排气阀是否发生堵塞,若发生堵塞必须及时采取措施加以清洗。

(5)先提钻后泵料    有些施工单位施工时,当桩端达到设计标高后,为了便于打开阀门,泵送混合料前将钻杆提拔30cm,这样操作存在下列问题。

①有可能使钻头上的土掉进桩孔。

②当桩端为饱和的砂卵石层时,提拔30cm易使水迅速填充该空间,泵送混合料后,混合料不足以使水立即全部排走,这样桩端的混合料可能存在浆液与骨料分离的现象。

这两种情况均会影响CFG桩的桩端承载力的发挥。

5.施工检验及验收

1)施工检测

CFG桩施上完毕,一般28d后对CFG桩和CFG桩复合地基进行检测,检测包括对桩身质量的低应变检测和对承载力的静载荷试验检测。对承载力的静载荷试验检测一般进行单桩复台地基静载荷试验或多桩复台地基静载荷试验,根据试验结果评价复合地基承载力,亦可采用单桩载荷试验,通过计算评价复合地基承载力。

检测数量一般遵守以下原则:静载荷试验数量取CFG桩总桩数的0.5%~1.0%,且每个单体工程的试验数量不少于3点;低应变检测桩的数量一般取CFG桩总桩数的10%选择试验点时应本着随机分布的原则进行选择。挑选施工质量好的桩或施工质量差的桩,或者为了检测方便将所有试桩集中在一个区域的选桩方法,都不能体现随机分布的原则。低应变检测取桩数10%进行检验时,建议采用下列方法选桩:选择0~9的任何一个数字,如选择5,那么桩编号个位数为5的桩均为试验桩,这样选择能够较好地体现随机分布的原则。

(1)CFG桩的检测

CFG桩单桩静载荷试验按《建筑地基基础设计规范》GB 50007-2002附录Q“单桩竖向静载荷试验要点”执行。

CFG桩低应变检测桩身质量评价分为以下四类。

Ⅰ类桩:完好桩;

Ⅱ类桩:有轻微缺陷,但不影响原设计桩身结构强度的桩;

Ⅲ类桩:有明显缺陷,但应采用其他方法进一步确认可用性的桩;

Ⅳ类桩:有严重缺陷桩或断桩。

(2)CFG桩复合地基的检测

CFG桩复合地基属于高黏结强度桩复合地基,载荷试验具有其特殊性,试验方法直接影响对复合地基承载力的评价。对此,试验时按《建筑地基处理技术规范》JGJ 79-2002“复合地基载荷试验要点”执行。

①褥垫层的厚度与铺设方法。试验时褥垫层的底面标高与桩顶设计标高相同,褥垫层底面要求平整,褥垫层铺设厚度为50~150mm,铺设面积与载荷板面积相同,褥垫层周围要求有原状土约束。

②当p-s曲线平缓的光滑曲线时,按相对变形值确定复合地基承载力。当以卵石、圆砾、密实粗中砂为主的地基,可取沉降比s/b或s/d等于0.008所对应的压力作为CFG桩复合地基承载力特征值。当以黏性土、粉土为主的地基,可取沉降比s/b或s/d等于0.01所对应的压力作为CFG桩复合地基承载力特征值。

2)CFG桩复合地基施工验收

CFG桩复合地基验收时应提交下列资料:

(1)桩位测量放线图(包括桩位编号);

(2)材料检验及混合料试块试验报告书;

(3)竣工平面图;

(4)CFG桩施工原始记录;

(5)设计变更通知书、事故处理记录;

(6)复合地基静载荷试验检测报告;

(7)施工技术措施。

桩的施工容许偏差应满足下列要求:

(1)桩长容许偏差不大于10 cm;

(2)桩径容许偏差不大干2 cm;

(3)垂直度容许偏差不大于l%;

(4)桩位容许偏差对满堂布桩的基础,桩位偏差不应大于0.4倍桩径;对条形基础,桩位偏差不应大于0.25倍桩径;对单排布桩,桩位偏差不应大于60mm。

四、实习心得

为期4周的实习已经结束了,我在4周的实习中学到了很多在课堂上学不到的知识,受益匪浅.现在我对这4周的实习做一个工作小结。

我的任务是打桩准备及打桩过程中的一些记录工作,这对本学期才学到这门功课的我来说是一个挑战,通过工人的帮助,老师的指导,让我顺利的完成了这次任务。

实习期间,我勤奋好学,谦虚谨慎,认真听取指导,对于别人提出的工作建议虚心听取。并能够仔细观察、认真记录、独立思考、综合分析,努力把学校学到的知道应用到实际工作中,尽力做到理论和实际的结合,同时培养了我执着的敬业精神和勤奋踏实的工作作风,也培养了我的耐心和素质。工作中,我能够做到服从指挥,与工作人员友好相处,尊重老师,工作认真负责,责任心强。并始终坚持安全第一,保质保量。

回想自己在这期间的工作情况,也有不尽如意的地方。对此我思考过,工作经验自然是一个因素,然而更重要的是工作的心态。

好的心态是一切工作的基本条件。在工作中我有了以下体会。

第一,要有坚持不懈的精神

作为在校生,我们不管到哪家公司,一开始都不会立刻给我们重要的工作做,一般都是先让我们熟悉公司的工作环境,在这段时间里很多人会觉得很无聊,没事可做,便会产生离开的念头,在这个时候我们一定要坚持,不能轻易放弃。

第二,要勤劳,任劳任怨

我们去公司实习,由于我们不是正式工作人员,所以公司多数就是把我们当学生看待。公司在这个期间一般不会给我们什么重要的工作去做,可又不能让我们闲着,因此,他们会交给我们一些比较简单的工作。与此同时,我们应该主动找一些事情来做,从小事做起,任劳任怨。

第三,要虚心学习,不耻下问

在工作过程中,我们肯定会碰到很多的问题,有很多是我们所不懂的,不懂的东西我们就要虚心向工友请教,当别人教我们的时候,我们应该虚心地接受。同时,我们也不要怕犯错。每一个人都有犯错的时候,工作中第一次做错了不要紧,重要的是知错能改,积极请教。

第四,要确立明确的目标,并端正自己的态度

平时,我们不管做什么事,都要明确自己的目标,就像我们到公司工作以后,要知道自己能否胜任这份工作,关键是看你自己对待工作的态度,态度对了,即使自己以前没学过的知识也可以在工作中逐渐的掌握。因此,要树立正确的目标,在实现目标的过程中一定要多看别人怎样做,多听别人怎样说,多想自己应该怎样做,然后自己亲自动手去多做。只有这样我们才能把事情做好。

通过本次的实习,我还发现自己以前学习中所出现的一些薄弱环节,并为今后的学习指明了方向,同时也会为将来的工作打下一个良好的基础。但这次的实习为我们提供了一个很好的锻炼机会,使我们及早了解一些相关知识以便以后运用到以后的业务中去。

总体来说,这次实习不仅仅是锻炼了我的一些技能,同时,经过这次实习,我还从中学到了很多课本上所没有提及的知识,应尽快学会在社会上独立,敢于参加与社会竞争,敢于承受社会压力,使自己能够在社会上快速成长。总的来说,作为一个快要毕业的大学生,无论是在今后的工作或是生活中,实习都将成为我人生中一笔重要的资本。

我会把这此实习作为我人生的转折点,在以后的工作学习中不断要求自己,完善自己,让自己做的更好。

五、附录

1.拟建建筑首层平面图

2.CFG钻杆钻头图

1.首层平面图

 


2.CFG钻杆钻头图

相关推荐